Product tour

One job, end to end.

One real job, moving through the app. The figures are left in so you can check each screen against the last.

Price

It starts with the estimate.

A real build-up on every line: the crew, the plant and the materials, each carrying its own cost code. Direct cost $129,950, contract $155,940. Hold those two figures.

An estimate: direct cost $129,950, contract $155,940, and one bill item opened to show what is behind its rate: a five-man crew with two 20-tonne excavators and a tipper, a wet-hire long-reach excavator, a float and a dewatering pump.
Direct cost $129,950.00, markup 20.0%, contract value $155,940.00. Item 1.02, Basin excavation and stockpile management, opened to its build-up: a five-man crew with two 20-tonne excavators and a tipper, a wet-hire long-reach excavator, a float and a dewatering pump.

Programme

The programme is the estimate, scheduled.

Days go against work you have already priced. Critical path, float and working-day calendars, and export to MS Project. Moving a date moves the cash flow and the claim with it.

A programme showing key dates and construction works as a linked Gantt chart, with milestones, predecessors and successors, and bars coloured by crew.
A project budget by cost code (labour, floats and transport, plant hire, site establishment, materials and landscaping) totalling $129,950.
Total direct cost $129,950.00, with a CSV export button. Budget by category: labour $40,000, floats and transport $3,610, dry plant hire $24,320, site establishment $4,250, materials $25,270, turf and landscaping $32,500. Total $129,950.

Win

The budget is the estimate, coded.

Built from the estimate's own lines, split by cost code, and it totals $129,950, the direct cost from the screen above. Not a number that got typed twice and happens to agree.

A progress claim with each bill item phased across August and September, the months summing to a $155,940 contract.
Contract $155,940.00, claimed to date $0.00, remaining $155,940.00. Each bill item phased across August and September by percentage, the two months' forecasts summing to the $155,940 contract.

Claim

The claim is the estimate, phased.

The two months come to $155,940: the contract the estimate produced. Item 1.02 splits 14.29 and 85.71 per cent because that is how the programme runs it, not because anyone typed it.

Still building the budget, programme and claim separately?

See it run on one of your own jobs.

How does it all connect?

The seven stages, from pricing the tender to the next job starting from real costs.